Lintasan Kritis January 19, 2009

Posted by abuhaidar18 in Kuliah.
trackback

ELEMEN KEGIATAN KEGIATAN ESTIMASI WKT

PENDAHULU (HARI)

A.Perancangan sistem – 10

B. Pemb.saluran air A 8

C. Pembuatan Fondasi A 9

D. Menata Furniture A 12

E. Pembuatan instlasi lstrk C 6

F. Pemasangan pipa B,C 7

G. Pemasangan mesin D,E 5

H. Finishing F,G 4


a.Tentukan Lintasan Kritisnya
b.Berapa hari penyelesaian proyek di atas ?
c.Jika pekerjaan C terlambat 1 hari, apakah mempenga-
ruhi terhadap penyelesaian proyek secara keseluruhan?

Jawaban :

download picture

dsc001951

Advertisement

Comments»

1. essajiwa - February 12, 2009

Wakakakakaka.. gw salaaaaah pas ujian… T_T

2. abuhaidar18 - February 13, 2009

ah pak essa ini selalu merendah, mantan anak ia01 gitu loh hehehehehehehehe


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.